Will non-cost resources impact EVM or CPI/SPI?
Technically if they have zero hours budgeted and zero
cost they don't impact planned value or Earned Value Ccost, but everything has
to be zero, including budgeted and actual hours. Verify that the resources do
not have auto compute actuals checked, which should ensure that no actuals are
calculated either. If actuals are calculated then Earned Value on hours would
be impacted