I would not change the remaining duration of an activity that hasn't started. I would go into the current schedule and change the original duration. This way, if you change in the current schedule you can measure that variance against the baseline that was taken. I think comparing current schedule to baseline (in P6) is a lot easier done than measure remaining duration changes.