Advice, Tools, and Suggestions on P6 EPPM, Pro, and Oracle Primavera Cloud
Pages
▼
Monday, April 13, 2015
I am updating a project schedule with resources and after updating I found that the remaining units/time for completed activity is still fixed 8h/d. Is this right?
Remaining units/time should tie back to the hours/day setting and correct, it should not be changed. the remaining units is what you can change.
No comments:
Post a Comment