Thursday, February 12, 2015
What happens when you use the Update Progress feature?
If activities are progressing on schedule, you may want P6 Professional to estimate progress for all activities as of the new data date you specify. P6 Professional can quickly apply actuals to activity dates, and calculate actual duration and units when you use the Update Progress dialog box to update activities.
Estimating activity progress is a quick and convenient way to update your project. P6 Professional estimates progress only for those activities that were supposed to take place. Since progress can occur on activities out of sequence, you may need to update additional activities—especially if you selected activities by dragging the data-date line or by using the Progress Spotlight feature (View, Progress Spotlight). Once you spotlight activities, you can quickly update the project automatically as "on time."
When you use Update Progress to progress activities, P6 Professional will apply actual dates to the activities that should have started and finished, update the actual and remaining durations, and update the remaining units according to the new data date.
how to assign multiple price /units to the same resource...can two budgeted cost columns viewed at the same time....
You can do this in the resources section. You can set two rates either by rate type or by effective dates. Usually you see a resource in one role and using one rate and then at a certain point in time takes on a new role and new rate. The rate type must correspond to the project rate type an only one rate type can be used per project. To clarify, you will have one rate type for the project. The resources that you use will need to have amounts populated in that rate type. You can use different rates for the same resource, but it's best to have them set to be effective at different dates or use an override. As for seing them in budgeted cost, the respective resource rate/costs will roll up to the budgeted costs for the activity. You can see budgeted assignment costs across resources in the assignment view.
I want to update progress for a number of activities.
Use the Progress Spotlight feature (View, Progress Spotlight) to highlight activities in the layout that have started, progressed, or finished between the previous data date and the new data date. If you have the project privileges required to schedule projects, level resources, and apply actuals, you can status the activities that have been highlighted.
Tuesday, February 10, 2015
Filter out activities which having over allocated resources.
In 8.x web you could also build out a view in the assignments section in resources. If you are looking on a more global scale. Need to group and sort by project/activity/resource and then figure out a period for which you are looking for and add columns for budgeted/planned units (time).
How do I use thresholds?
It is your choice how you want to use thresholds. You can use them on performance, schedule and index. They can be added to the dashboard portlets and they can be configured in administer>my preferences. It's really up to you but you can use them to show as of today and forecast to be complete for schedule performance. Same with cost and index.
Friday, February 6, 2015
I have negative float in my project. How can I fix this?
Check the total float by adding the Total Float column into your schedule. This will show the negative data. Then from there you can backtrack up the schedule to determine what is driving these negative floats. It could be a number of things. Out of sequence activities, non-progressed schedule, wrong finish dates or durations.
Thursday, February 5, 2015
I want to pause an activity. How can I do this?
you can use the suspend/resume dates fields. The date work has temporarily stopped on a given activity.
For example, an event might force an activity to be interrupted or resource constraints might put an activity on hold. The suspend date must be later than the actual start date, which the activity must have. Activity progress can resume when the Resume Date is set. The suspend/resume period behaves like non-work time on the activity calendar or resource calendar for task and resource dependent activities.
Resume Date field -The date when a suspended task or activity is resumed.
The resume date must be later than the suspend date and earlier than the actual finish date.The suspend/resume period behaves like non-work time on the activity calendar.
For example, an event might force an activity to be interrupted or resource constraints might put an activity on hold. The suspend date must be later than the actual start date, which the activity must have. Activity progress can resume when the Resume Date is set. The suspend/resume period behaves like non-work time on the activity calendar or resource calendar for task and resource dependent activities.
Resume Date field -The date when a suspended task or activity is resumed.
The resume date must be later than the suspend date and earlier than the actual finish date.The suspend/resume period behaves like non-work time on the activity calendar.
What is better for importing, XLS or XML or XML from MSP?
Importing project data from MSP is definitely better than using an XLS file. Primavera, both the client and web support importing XML files. There are out of box import options for XML and XML MSP files, so that Primavera will look at the fields that are in MSP and migrate the data to the fields that are in P6. When doing these imports using XLS, you really have to get the naming conventions spot on, the fields have to be perfect, the data in the fields needs to be perfect. If you can get the XML out of MSP, most of the fields/attributes are already housed in P6 for the import. There is TONS of support in the user guide for working with XML files and working with MSP and XML files. The user guide lists the following for XML imports. docs.oracle.com
Tuesday, February 3, 2015
Creating a filter. Can I use unlimited Parameters within one filter? What am I overlooking? It will only filter my chosen parameter with a Start & Finish. Three lines total.
Are you using client or web? You can use a number of parameters, but depending on the details of those parameters and if they are looking for different items in the same topic, there is a chance they cancel each other out and give back no results. When setting up filters, make sure to carefully select "all" or "any" and how you set up the filter with "and" and "or".
example
example
| Display all rows | Parameter | Is | Value | High Value |
| Filter Item: (Any of the following) | (Any of the following) | |||
| Where | (All of the following) | |||
| Where | Start | is less than | CD | |
| And | Finish | is greater than | CD | |
| Or | (All of the following) | |||
| Where | Start | is greater than | CD | |
| And | Start | is less than | CD+2W |
How do I update activity ID's?
It might be best to take a new baseline since it seems like you have changed the schedule. In the client you need to have rights to change the activity ID's (most likely defined in your project security role). So you can do it without re-baselining. Just need to make sure you have that access. In web, Administrator>User Access>Project Security Profile>Activity>Edit Activity ID.