I want to see in progress or not started activities.

You can run a report in P6 client to report on these. A simple filter will get you there. Maybe try one filter at a time, but I think you could do one that was two-tiered asking for "any" activities that are in progress or not started. This is something that many planners/schedulers look at, so very common problem.