PM wants to retroactive hours to project after project has been baselined.

Even though the project has been baselined, there is no rule that says we have to put it in job services. It can be baselined, you guys can charge your time retroactively and when ready, we can apply actuals and schedule the project. And it will pick up the actuals and activity progress up to the future data date. I think this might be a better route than I originally suggested because the positive impact is twofold and you will still have the project baselined.