What is Planned Value Cost?

If an activity has no resources, its Planned Value Cost is calculated as the Budget At Completion * Schedule % Complete [(Data date - Baseline Start) / (Planned Finish - Baseline Start)]. The Schedule % Complete specifies how much of the activity's original or planned duration has been completed so far.