User has a cost-plus contract and wants to cap resource hours so overtime is not adding additional costs.

Go resource details tab in resource dictionary. Check off “Overtime Allowed” and change the overtime factor to zero. Resource can only charge actuals through Progress Reporter for this to be applicable